Wednesday, 4 December 2013

Framework

The framework was estimated to take about two weeks.


After two days, Master Bedroom on left, WIR behind that and ensuite behind that, with entry porch in the middle.


And these two, a week later. View from the street, looking like a house. Upstairs on the right is the spare bedroom, and the room to the left of that is the room at the top of the stairs. 


View of Master bedroom with power box, windows leaning against WIR/Ensuite, and upstairs above the Master Bedroom are the two girls' bedrooms.